NewlinesADU — A Division of Newlines ContractingClient portal
Your home, step by step

Bracken replacement home

Davis replacement home · Squamish
Your project at a glance
Reviewed November 24, 2026
Preconstruction · Permit intake

Building Permit
pending.

The District accepted the Building Permit application on November 10. We’re finishing the remaining design and permit work.

Issued Development PermitIssued Soil Permit

Site work follows permits and a signed construction contract.

Illustrative design of the raised Davis home
Design direction · Illustrative rendering
What happens next

Finish design and permitting

Complete the remaining design coordination and respond to the District’s requirements.

  1. 01
    Receive the required permitsMunicipal approvals before site work.
  2. 02
    Confirm pricing and prepare the fixed-price contractAfter the required permits are in.
  3. 03
    Confirm the schedule and startAfter the construction contract is signed.
Your action

Send the trailer dimensions

Please send the trailer’s overall length and its width with the slides out. The driveway needs to stay clear for construction.

We’ll check whether the trailer can fit at the back and, if it fits, confirm with the District whether you can stay in it during construction. In the meantime, keep your rental options flexible.

Your design decision is saved

The deck, steel structure and HSS bracing are staying. No repeat decision is needed.

Key documents

IKON’s set is labelled “Issued for Construction”. Municipal permits and a signed construction contract are still required before site work begins.

Previous project updatesView history

Dated records below describe the project at that time. The current position is shown above.

Development Permit issued and Building Permit package sent

The signed Development Permit has been received. The current Building Permit package has been sent to the District, with intake confirmation still pending.

Client action

None at this time.

Development Permit registration underway

The signed Development Permit is now with District Corporate Services for registration. The permit has not yet been formally issued.

What happens next

Receive the issued Development Permit, complete the remaining pile and steel-connection engineering, then submit the Building Permit application.

Client action

None at this time.

Structural permit drawings received

We received IKON’s sealed foundation and steel drawings for the Building Permit application on October 16. Click Modular’s stamped home drawings have also been received and shared with IKON.

We are now coordinating the remaining pile and steel-connection engineering and preparing the permit package.

What happens next

Complete the remaining engineering documents and confirm formal issuance of the Development Permit before moving ahead with the Building Permit submission.

Client action

Nothing needed from you at this stage.

These drawings were issued for the permit application. They do not authorize construction.

We recommend keeping stainless steel.

We received updated appliance pricing from Patrick at Trail Appliances. Switching the two major items he reviewed to white would save only $40. Given the small difference, we recommend keeping the stainless steel option.

Development Permit signed.

The District has confirmed that the Development Permit is signed and awaiting registration before it is formally issued. This is an important step forward, but the permit has not been issued yet.

Client action: None required.

Site-preparation planning is moving forward.

We have identified a preferred contractor for demolition, excavation and site services. We are now reviewing the scope and looking for practical cost savings before final pricing is confirmed.