Building Permit
pending.
The District accepted the Building Permit application on November 10. We’re finishing the remaining design and permit work.
Site work follows permits and a signed construction contract.
The District accepted the Building Permit application on November 10. We’re finishing the remaining design and permit work.
Site work follows permits and a signed construction contract.

Complete the remaining design coordination and respond to the District’s requirements.
Please send the trailer’s overall length and its width with the slides out. The driveway needs to stay clear for construction.
We’ll check whether the trailer can fit at the back and, if it fits, confirm with the District whether you can stay in it during construction. In the meantime, keep your rental options flexible.
The deck, steel structure and HSS bracing are staying. No repeat decision is needed.
IKON’s set is labelled “Issued for Construction”. Municipal permits and a signed construction contract are still required before site work begins.
Dated records below describe the project at that time. The current position is shown above.
The signed Development Permit has been received. The current Building Permit package has been sent to the District, with intake confirmation still pending.
None at this time.
The signed Development Permit is now with District Corporate Services for registration. The permit has not yet been formally issued.
Receive the issued Development Permit, complete the remaining pile and steel-connection engineering, then submit the Building Permit application.
None at this time.
We received IKON’s sealed foundation and steel drawings for the Building Permit application on October 16. Click Modular’s stamped home drawings have also been received and shared with IKON.
We are now coordinating the remaining pile and steel-connection engineering and preparing the permit package.
Complete the remaining engineering documents and confirm formal issuance of the Development Permit before moving ahead with the Building Permit submission.
Nothing needed from you at this stage.
These drawings were issued for the permit application. They do not authorize construction.
We received updated appliance pricing from Patrick at Trail Appliances. Switching the two major items he reviewed to white would save only $40. Given the small difference, we recommend keeping the stainless steel option.
The District has confirmed that the Development Permit is signed and awaiting registration before it is formally issued. This is an important step forward, but the permit has not been issued yet.
Client action: None required.
We have identified a preferred contractor for demolition, excavation and site services. We are now reviewing the scope and looking for practical cost savings before final pricing is confirmed.
Explore each phase, or switch to dated milestones for the project history.
From planning to your new Click Modular Davis home.
The Building Permit is pending while final design and permit work continues.
Your construction schedule
A preliminary view of the current plan. Dates may change as permits, engineering, materials and trade availability are confirmed.
Please confirm move-out and return dates with us before booking accommodation. The occupancy window is a forecast, not a confirmed move-in date.
Now
Before site work
Before delivery
All activities are shown on each day they span. Select an activity for its dates and details. A span does not confirm attendance every day, and weekends are not weekend bookings. All dates use the Vancouver project calendar.
Loading the current schedule…
The current schedule is unavailable. Please try Refresh schedule. Confirm timing with us before making plans.
Working estimate shared September 23, 2026. After we receive the required permits, we’ll confirm the remaining construction pricing and prepare the fixed-price construction contract.
Before GST · Not a fixed-price contract
Open the working estimate · Public copyThe estimate shows the scope, allowances and detailed breakdown.
The September delivery quote was approximately $16,000 all included, including ferry. This has not been deducted from the budget above. Delivery is one part of the delivery, crane and installation scope.
After permits, agree the final scope, inclusions, exclusions, fixed price, payment schedule and construction timing. Review and sign the fixed-price construction contract, then confirm the schedule and start site work.
The public copies omit personal details. Contact Newlines for the original project documents.
November 10, 2026 · Issued for Construction · Public reference copy
Open structural drawingsDevelopment Permit DP000660 · Received October 30, 2026. Contact Newlines for the original.